Implementing iCare at your center is a simple process that takes one to two weeks, including:
§ Hardware and software installation and setup§ Learning the software§ Initial data entry§ On-line trainingAppoint a project manager, usually the center director, who will monitor the installation process and receive training from Orgamation. The project manager should refer to the following table for organizing the implementation process:| # | Task | What to do |
|
1 |
Hardware Shipment |
Project Manager to compile needs for Orgamation |
|
2 |
Software Installation |
1. Install iCare 2. Install LogMeIn or other remote maintenance software |
|
3 |
Install LAN and Data Terminals, Door Openers, Signature Tablets and Lobby Interface |
Installation and Testing Instructions included in this manual |
|
4 |
System Priming and Registration |
Priming sheet to be entered by Project Manager and faxed to Orgamation |
|
5 |
Software System Training |
Refer to this Manual Schedule on-line training with Orgamation (free with MIS support plan or charged per instance) |
|
6 |
Initial Data Entry or Data Transfer |
Data transfer service available from Orgamation |
|
7 |
Implementation Check |
Use iCare Implementation Check List |